HOW ARE YOU ABLE TO LIEN A JOB WITH MULTIPLE DIRECT CONTRACTS?

The following article was written by Miami Construction Lawyer Alex Barthet and appeared first on TheLienZone. It was re-posted with permission. For more information about Alex and his firm, please visit www.TheLienZone.com and www.Barthet.com.

See below for some great information we found on liens. Do not ever hesitate to call us here at Licenses, Etc.! If we don’t have the information, we can find it for you!

We’ve often written about it – how do you lien a job with multiple direct contracts? Do you file a blanket lien incorporating all the improvements arising out of these several contracts? After all, they’re all related to the same property. How many liens do you need?

HERE’S WHAT YOU HAVE TO DO

You must file a separate lien for each direct contract. Take a shortcut and file only one lien to address various direct contracts on the same property and you could well lose your lien rights. We should know. We recently argued such a case on behalf of our condominium association client and won.

On April 17, 2015, The Daily Business Review reported:

“In a cautionary tale for contractors to dot their i’s and cross all their t’s, a Miami-Dade Circuit Judge has thrown out a lien due to what’s essentially a rookie mistake. The judge delivered a blow to an engineering firm suing a Miami Beach Condominium association for non-payment.”

DON’T MAKE THIS MISTAKE

The judge vacated the lien that had been filed against our client because it failed to comply with applicable Florida law. The engineer had entered into 9 separate contracts for concrete and stucco work, replacement windows, sliding glass doors, cabanas and a new entrance. It then added all the monies still owed under the 9 contracts into one lien, something the law does not allow.  Clearly, the consequences for any contractor, or in this case, an engineer, relying on what ended up being a faulty filing to secure payment can be costly. Liens can be filed only within 90 days of work being performed and once those 90 days expire, there’s no fixing the error of having filed just one lien to cover multiple contracts. Don’t make this mistake. Make sure your critical liens are reviewed by a construction lawyer, especially if you’re not totally familiar with the lien law which unfortunately is  very unforgiving.

At Licenses, Etc., we offer a fast contractor license application process for our contractor clients. Contact us about getting your Florida contractor’s license by clicking here or calling 239-777-1028.

Leave a Reply

how can we help you?

Contact us at the Consulting WP office nearest to you or submit a business inquiry online.

Looking for a First-Class Business Plan Consultant?