- November 15, 2019
- Posted by: admin
- Category: Contractor Legal Information, Florida Contractor License

The following article was written by Miami Construction Lawyer Alex Barthet and appeared first on TheLienZone. It was re-posted with permission. For more information about Alex and his firm, please visit www.TheLienZone.com and www.Barthet.com.
See below for some great information on liquidated damages. Do not hesitate to call us here at Licenses, Etc.! If we don’t have the information, we can find it for you!
Anyone regularly reviewing construction contracts will come across those dreaded liquidated damage clauses. They require contractors, and in turn subcontractors, to make significant payments to compensate for late completion of work – $100-$500-$1,000 per day wouldn’t be unusual. But are these big dollar payment demands enforceable?
Most of these clauses are written with standard disclaimers. They state that actual damages will be difficult if not impossible to determine if there is a breach. So let’s agree in advance to a number, and let’s also agree that this is not a penalty. Why is this language incorporated? Simple. The owner and the general contractor want to preempt the potential defenses that could be raised when damages are assessed. However, these attempts to make their liquidated damages stick may not always work.
If the amount “agreed” on by the parties is unconscionable and just too high, a court could reject it as an unreasonable assessment. Also, just saying something is not a penalty isn’t necessarily enough. The facts of each case will determine that, and circumstances showing that someone was coerced into agreeing could well negate the assessment of those damages.
As well, liquidated damages can often be defeated if it can be shown that the one being assessed these damages was not the sole cause of the delay. As we all know, in construction, it is not uncommon to have multiple parties contribute to any late completion on a project.
For sure, try to strike or significantly limit the liquidated damage language in any contract you sign. If that doesn’t work, all is not lost. Enforcement is never a sure thing and seeking the advice of a board certified construction law expert should be your next step.
At Licenses, Etc., we offer a fast and easy contractor license application process for our contractor clients in Florida and other states. We are a Florida contractor licensing company. Contact us at Licenses, Etc., to get your Florida contractor’s license today by clicking Florida contractor’s license page or calling 239-777-1028.
Leave a Reply
You must be logged in to post a comment.