When Can You Be Paid that Retainage?

The following article was written by Miami Construction Lawyer Alex Barthet and appeared first on TheLienZone. It was re-posted with permission. For more information about Alex and his firm, please visit www.TheLienZone.com and www.Barthet.com.

See below for some great information on getting paid that retainage.  Do not hesitate to call us here at Licenses, Etc.! If we don’t have the information, we can find it for you!

Retainage is a part of every pay application, especially on a commercial job. But you may be in luck if you’re working for a local municipality. That’s because at 50 percent completion “… most public entities must reduce to 5 percent the amount of retainage withheld from each subsequent progress payment made to the contractor”. The term “50-percent completion” means the point at which the public entity has expended 50 percent of the total cost of the construction services purchased as identified in the contract, together with all costs associated with any existing change orders and other additions or modifications to the contract.

Florida Statutes state that after 50-percent completion the contractor may present to the public entity a payment request for up to one-half of the retainage held by the public entity and it means the public entity shall promptly make payment to the contractor, unless the public entity has grounds for withholding the payment of retainage. Pretty straight forward.

A general contractor, on the other hand, may elect to withhold retainage from payments due to subcontractors at a rate higher than 5 percent. The specific amount to be withheld must be determined on a case-by-case basis and must be based on an assessment of the subcontractor’s past performance, the likelihood that such performance will continue, and an ability to rely on other safeguards. The subcontractor must be notified in writing of any determination to withhold more than 5 percent of the progress payment and the reasons for making that determination.

On a private job, retainage, both as to amounts withheld and amounts released, is strictly based on what has been contracted. While most contracts call for the owner to retain 10 percent of each payment request till final completion, know that one is free to negotiate both the amount to be withheld as well as the timing on when a portion or all of that amount is released.

At Licenses, Etc., we offer a fast and easy contractor license application process for our contractor clients in Florida and other states. We are a Florida contractor licensing company. Contact us at Licenses, Etc., to get your Florida contractor’s license today by clicking Florida contractor’s license  page or calling 239-777-1028. 